Ansal Housing Amantre Price List
Price List | |
Basic Sale Price | Rs. 7000 Per Sq.Ft. |
Inaugural Discount | Rs. 250 Per Sq.Ft |
Effective Price | Rs. 6750 Per Sq.Ft |
EDC / IDC | Rs. 382 Per Sq.Ft. |
First Car Parking | Rs. 375000 Per Sq.Ft |
Additional Car Parking (Mandatory for 4 BHK Apartment only) | Rs. 375000 Per Sq.Ft |
Labor Cess | Rs. 23 Per Sq.Ft |
IFMS | Rs. 100 Per Sq.Ft |
PLC | As Applicable |
Club Membership | Rs. 175000 Per Sq.Ft |
Payment Plan | |
Assured Buyback Plan | |
On Booking | 15% of Gross Value |
Within 3 Months | 10% of Gross Value |
Within 6 Months | 10% of Gross Value |
Pay 35% in first 6 month, then no- payment till 3 years. After 3 years, you have choice to surrender unit to ansals with assured buy back returns starting 1100/sqft or continue with unit and pay rest 65% ,according to CLP easy payment plan. | |
Note:-
|
|
Possession Linked Payment Plan | |
Booking Amount | Rs. 5,00, 000/- |
Within 60 days of Booking | 20% of BSP + PLC less booking amount + 100% Labor Cess |
On Completion of Super Structure | 20% of BSP + PLC + 100% Club Membership |
On Application of OC/CC | 60% of BSP + PLC + 100% Car Parking & Other Allied Charges |
Construction Linked Payment Plan | |
On or Before 90 days from Registration | 15% Balance to Complete |
At the time of Allotment or on or before 300 Days whichever is earlier | 10% of BSP |
On Commencement of Construction | 6% of BSP + Labor Cess |
On Completion of Raft | 6% of BSP |
On Commencement of Basement Roof Slab | 6% of BSP |
On Commencement of 1st Floor Roof Slab | 6% of BSP |
On Commencement of 3rd Floor Roof Slab | 6% of BSP + 50% PLC |
On Commencement of 5th Floor Roof Slab | 5% of BSP + 50% PLC |
On Commencement of 8th Floor Roof Slab | 5% of BSP |
On Commencement of 11th Floor Roof Slab | 5% of BSP |
On Commencement of 14th Floor Roof Slab | 5% of BSP |
On Commencement of Top Floor Roof Slab | 5% of BSP |
On Completion of Brickwork of Floor on which the unit is allotted | 5% + External Electrification Charges |
On Commencement of External Plaster | 5% + Fire Fighting Charges |
On Commencement of Flooring of Unit | 5% + Power Back Up Charges |
On Offer of Possession Letter | 5% Balance Basic cost with balance allied charges, if any and IFMS and Maintenance Charges |
Notes:-
|
Interested ? Send Email Enquiry