Construction Linked Payment Plan |
Payment Schedule |
Basic Sale Price (including PLC) |
EDC & IDC |
Booking Amount |
Rs. 25 Lacs |
|
30 days from Booking |
25% (less booking amount paid) |
|
60 days from Booking |
-- |
100% |
On completion of foundation work or 1st June2015, whichever is later |
10% |
|
On completion of basement roof slab or 90 days from the PRL date of completion of foundation work, whichever is later |
10% |
|
On completion of ground floor roof slab or 90 days from the PRL date of completion of basement roof slab, whichever is later |
10% |
|
On completion of first floor roof slab or 90 days from the PRL date of completion of ground floor roof slab, whichever is later |
10% |
|
On completion of second floor roof slab or 90 days from the PRL date of completion of first floor roof slab, whichever is later |
10% |
|
On completion of block work excluding shafts, ducts etc. |
5% |
|
On completion of internal plastering excluding shafts, ducts |
5% |
|
On completion of internal flooring |
5% |
|
On handover / offer of handover |
5% |
|